Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Table of Contents

...

  • Go to Playbook tab > click the Settings button

  • Toggle the button to enable Staging

  • Select Event behavior Event Behavior (See descriptions of the Event Behavior below)

  • Select Sales Process

  • Save 

...

Event Behavior

Setting event behavior affects the behavior of events and the subsequent movement to other sales stagesEvent Behavior can affect the User’s ability to advance through the Sales Stages in the Sales Process.

  • Block if Event is required - Event can be Playbook Events are set as required. If so, users Users will be prevented from moving to the next Stage until the required Event is set to Completed.

    • If the Event is in any status other than ‘Completed’, Users will be prevented from moving to the next

    stage until the required Event is completed.
    • Stage.

      • Example: Even if all Checklist items are ticked, but the Event is still ‘In Progress’, (or in any status other than Completed) Users will be prevented from moving to the next Stage.

      • Image below showing different Event Statuses: Completed (Green), In Progress (Yellow), Not Started (Blue)

...

  • Auto-Complete open Event - Event  Indicates the Event is set as not required.  Users can move to the next stage Stage even if there is an uncompleted Event .is not Completed

  • Block if Event is required, otherwise Auto-Complete Event - This setting allows for a combination of the 2 settings above.

    • If there is a required Event, Users will be blocked from moving to the next Stage until the Event is set to Completed.

    • If the Event is not required to move to the next

    stage
    • Stage,

    otherwise
    • Users

    can
    • are permitted to move to the next

    stage
    • Stage regardless of the Event status.  

Sales Process

The selected Sales Process is displayed as Sales Stages in the Playbook. Sales Stages contain Events.

...

 Required =  Event can be closed only after the Event upon which it is dependent is completed and closed.

 Not Required = Event can be closed without completing or closing the Event upon which it is dependent.

...

  • Click on the Event name to open the event

  • Go to Dependency tab and click on Add dependency

  • Select a target event and mark if the target event will be required as completed in order to complete this Event

  • Save 

          

  • Add additional dependencies if needed and Save

...

  1. Toggle Sidebar - Toggles visibility of the Sidebar.

  2. Switch view between days and months.

  3. Scroll buttons - Scroll the Gantt area to Start, left, right or to the End

  4. Export data as Excel, PDF, Image or MS Project

  5. Add a new Event

  6. Event Stage -  click 

     to hide Events from view.

  7. Dependency button - hover over the event corner > click the button and drag the dependency line to the desire event. 

  8. Event Bar - Double click to open the Event, hover over the event bar corner to extend or shorten the event bar, click 1x to move the event right or left

  9. Not required dependency (grey)- to delete it click 2x on the dependency line and click Delete.

  10. Required dependency (orange) - to delete it click 2x on the dependency line and click Delete.

...

Individual data can be propagated on the Opportunity layout or in the Reports. 

Settings are made to the template from which you want to propagate data. If there are multiple active templates, you need to set up sync for each template from which data will be propagated.

To assign the sync, the custom fields on the Opportunity or ClosePlan Object need to be created. To propagate data to the Opportunity layout, the custom fields need to be created on the Opportunity Object. 

...

  • Save

  • Repeat steps to set sync for other events


Info

Note: Event Status picklist found on CP:Event is a Custom Field Definition and is part of the managed package. Modifying the Status picklist can adversely affect the application, unless explicitly stated. In general, any field or picklist that can be modified is accessible through the ClosePlan Admin tab. If any changes are needed to the Status Picklist, please coordinate with Engineering by sending the request to Support@People.ai